On 20 October 2026, the Syrian outlet Iqtisadi published a status check on the country's major telecom projects. Its framing: SilkLink, the Ebla cable and Barq Net are moving from announcements and memoranda toward contracting and implementation. Barq Net is described as the first to be placed under implementation, while economist Younes Al-Kareem says the Ebla cable is still at the preliminary-agreement or MoU stage. The article gives no specific SilkLink construction milestones.

The report describes SilkLink as a national fiber network of about 4,500 km with up to 100 Tbps of capacity, linking major cities, data centers and border crossings. Researcher Mulham Jazmati of Karam Shaar Advisory told the outlet that the projects are moving from announcements toward contracting and implementation, and that they work as one system:

  • Ebla for international capacity;
  • SilkLink for the national backbone;
  • Barq Net for the last mile.

The challenges

The report's sources list several obstacles. Researcher Mulham Jazmati cites unstable power, Syrian Telecom's control of the backbone and international gateways, limited correspondent banking and reliance on imported equipment; economist Younes Al-Kareem cites cable theft and the absence of an anti-monopoly law. The Ministry of Communications had not answered the outlet's questions on progress by the time of publication.

In an analysis published on 12 August 2026, Umran Syria says the 18-to-24-month timeline disclosed in February 2026 implies completion between August 2027 and February 2028.

What it means for infrastructure

2026 is best described as a year of contracting and preparation, not of a finished network: no specific construction milestones for SilkLink have been reported yet. The challenges listed, from power to cable theft, are the same ones every fiber project in Syria faces, and they call for careful route planning, physical protection and precise documentation.

Sources: Iqtisadi, Umran Syria